Grasshoppers Building Works

Regular newsletters will be issued by the contractor DAWNUS.

Newsletter No.1 (July 2017) introduces Dawnus, gives contact numbers and explains what will happen in general terms.

Newsletter No.2 (October 2017) continuing with the pitch works. Seeding work started.  Steel frame to the workshop completed, pouring the ground bearing slab, erecting the external blockwork and cladding the structure. The retaining walls to the clubhouse have commenced with the view to them being completed by the week-ending 29th October 2017.